Save Ontario $500 million (and save environment too): cancel Amherst Island wind power contract say citizens

Ottawa Wind Concerns

August 29, 2016

The Windlectric wind power project on tiny Amherst Island has no hope of meeting its “drop-dead” Commercial Operation date, so Ontario’s Independent Electricity System Operator (IESO) can cancel the Feed In Tariff (FIT) contract right now, with no penalty, says the Association to Protect Amherst Island.

See the letter to IESO Chair Tim O’Neill here and below.

header-12.jpg

Dear Dr. O’Neill,

In August 2015 The Association to Protect Amherst Island requested that the IESO exercise its ability to cancel the Fit Contract dated February 25, 2011 with Windlectric Inc. (Algonquin Power) without penalty because of the inability of the company to achieve its commercial operation date.

In its 2016 Q2 Quarterly Report, extract attached, Algonquin now advises that construction is expected to take 12 to 18 months and that the Commercial Operation Date will be in 2018. This timeline is contrary to what was submitted to the Environmental…

View original post 301 more words

Advertisements
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s